Commissioning Your BTC Charging Stations
Follow these steps to commission commercial charging stations quickly and ensure easy activation for your customers.
Required Information for Commissioning
Please provide the following details to proceed with commissioning:
- Commissioning form (completed by the owner)
- Installation validation checklist (completed by the installer)
- Final installation date (provided by the installer)
- Requested commissioning date (provided by the owner)
Complete the Installation
Fully complete the installation validation checklist.
Submit the Documentation
Send the completed checklist to: client.integration@flo.com
Notify FLO
Once the installation is complete, contact our team at: 1-888-852-3518
Technical Validation (if required)
- If any issues are identified, a FLO or BTC technician may be dispatched
- Possible delay: up to 2 weeks
Station Activation
Once the file has been reviewed and approved, the charging station will be activated as quickly as possible.
Installation Guide
Download the installation guide (PDF)
Access the complete guide to support you during installation and ensure all technical
requirements are met.